TITLE:Internal Network Reconstruction Study, Wastewater Adduction Works and Wastewater Treatment Plant (WWTP) of St. George Settlement
NAME OF CLIENT:Municipality of Livadia
TYPE OF SERVICES PROVIDED:Plumbing & E / M Preliminary Wastewater Networks Study, Preliminary WWTP Study (Hydraulic, E / M, Chemotechnical), Final Wastewater Networks Hydraulic Study
NAME OF LEGAL ENTITY:HYDROMENT – ENGINEERING CONSULTANTS S.A.
PROJECT CONSTRUCTION CONTRACTOR:
DATES (START):2014
DATES (END):2015
PLACE:Municipality of Livadia, Viotia Prefecture
DETAILED DESCRIPTION OF PROJECT:Part 1: Internal Sewerage Network and Supply Pipe
The proposed internal sewer network for St. George settlement, has a total gravity pipe length of about 16,4 km.

Part 2: Wastewater Treatment Plant
The Wastewater Treatment Plant (WWTP) of St. George settlement was designed in two phases, the first phase (with a planning period of 20 years) and the second (with a planning period of 40 years), to serve a maximum population of 5,000 6,600 residents respectively. The selected method of treatment is the Activated Sludge System with extended aeration membranes (MBR).